RAMS for Accreditation: What Schemes Actually Want in a Risk Assessment and Method Statement
RAMS for CHAS accreditation: assessors want site-specific risk assessments and method statements from a real job in the last 12 months, not templates. Here's the fix.

Last reviewed: 27/11/2026
If you've been knocked back on RAMS for CHAS accreditation — or for SafeContractor, SMAS, Acclaim or Constructionline — it's almost never because your wording was wrong. It's because you sent a generic template with no job on it, or an example from a project you did three years ago. Schemes assess RAMS as evidence that you actually planned a real piece of work, not as a library of documents you own. That distinction is the whole game, and it's the bit nobody tells you before you upload.
TL;DR
Every SSIP member scheme assesses risk assessments and method statements under Core Criterion 10, "Risk assessment leading to a safe system of work", and asks for site- or project-specific examples from a project carried out within the last 12 months (SSIP Core Criteria). A risk assessment is a legal duty; a method statement generally is not, but it's the standard way of showing how you'll control what the assessment found. Generic, undated, off-the-shelf RAMS are the single most common reason small subcontractors get a clarification request. The practical fix is to keep two or three real, dated job packs from the last year — not a folder of blank templates. And because the 12-month window rolls, your RAMS evidence effectively ages out even when your certificate hasn't.
What are RAMS, and are they a legal requirement?
RAMS is site shorthand for two separate documents that usually travel together: a risk assessment (what could hurt someone, who, and what you're doing about it) and a method statement (the step-by-step sequence of how the job gets done safely).
The risk assessment is the legal half. Under the Management of Health and Safety at Work Regulations 1999, employers must make a suitable and sufficient assessment of risk, and the Health and Safety Executive's guidance sets out the five steps — identify hazards, assess the risks, control the risks, record your findings, review the controls. The HSE states that if you employ five or more people you must record your significant findings: the hazards, who might be harmed and how, and what you're doing to control the risks (HSE, Managing risks and risk assessment at work).
The method statement is the other half, and CHAS's own guidance is straightforward about its status: method statements are generally not a specific legal requirement in Great Britain, but they're treated as best practice for complex and higher-risk tasks, and clients and regulators routinely ask for them (CHAS, risk assessment vs method statement).
What do assessors want in RAMS for CHAS accreditation and other SSIP schemes?
All SSIP member schemes assess against a shared threshold standard, so the RAMS requirement is broadly the same whichever door you walk through. SSIP Core Criterion 10 asks suppliers for documented procedures covering hazard identification and the development of safe systems of work, plus examples for the work categories being assessed:
- site or project specific risk assessments created for a project within the last 12 months
- site or project specific safe systems of work or method statements from a project within the last 12 months, where applicable
- COSHH assessments for any hazardous substances used, where applicable
SSIP also builds in proportionality: a supplier employing four or fewer people that doesn't have written arrangements should be able to describe how it identifies hazards and completes risk assessments (SSIP Core Criteria). That is a genuinely useful concession for a two-man firm — but it is a floor, not a target, and most main contractors will still want paper.
The schemes themselves say the same thing in their own words. CHAS states that assessors review policies, training, insurance, maintenance records, construction phase plans and COSHH procedures, and that your risk assessments and method statements "play an important role" (CHAS contractor health and safety assessment). SafeContractor lists risk assessments and method statements among the core documents for SSIP certification (SafeContractor). And the Once For All Health & Safety SSIP question set used for Constructionline is blunt: risk assessments must be site or project specific, the method statement must contain the systematic sequence in which the task is carried out, and evidence must be dated within the last 12 months (Once For All Health & Safety SSIP Question Set, October 2025).
| What you upload | How it usually lands |
|---|---|
| Blank template with your logo on it | Clarification request — no project, no date, no evidence of use |
| Generic "electrical works" RA covering everything you do | Partial credit at best; treated as an arrangement, not an example |
| Dated RA + MS for a named job done 4 months ago | What the criterion is written for |
| Same pack, but from a job in 2023 | Outside the 12-month window; expect to be asked for a newer one |
Why do generic RAMS templates fail?
Because the assessor isn't grading your prose — they're checking whether the controls match the work you actually sell. A risk assessment that lists "slips, trips and falls" and "manual handling" for every job tells them nothing about whether you understand isolation, permit control or working in an occupied building.
SSIP's own guidance on RAMS makes the point that assessors expect examples reflecting the type of work the organisation performs — working at height for roofers, COSHH assessments for cleaning contractors — and that documents do not need to be long or complex, as long as hazards are clearly identified and controls are realistic (SSIP, Risk Assessments and Method Statements).
That cuts both ways, and it's good news for a reluctant administrator: a short, specific, dated two-pager beats a 30-page generic bundle. Length is not what's being measured.
What does a passing risk assessment and method statement look like?
Take an illustrative example. Say a 12-engineer electrical and mechanical firm replaces a distribution board over a weekend in an occupied retail unit — two engineers, two days, live isolation, work at height off a podium step, and a shared corridor used by the client's staff.
- 1Name the job on the document. Client, site address, dates, who wrote it, who signed it, review date. An undated, unsigned, unnamed document is the number one reason a pack gets bounced back.
- 2List the hazards that are actually on that job. Live working and stored energy, work at height at the board, manual handling of the new panel, dust from any builders' work, members of the public and client staff in the corridor.
- 3Say who could be harmed. Your two engineers, the client's staff, cleaners, and anyone using the corridor — not just "operatives".
- 4State the controls in the words of the trade. Safe isolation to GS38 practice, lock-off and caution notices, proving unit tested before and after, podium step inspected, barriers and signage to the corridor, supply shutdown agreed with the client in writing.
- 5Write the method statement as a sequence, not a list. Arrive and induct, isolate and prove dead, barrier off, remove old board, install and terminate, test and certify, re-energise, hand back, clear site. Add emergency arrangements and who to call.
- 6Attach what the controls rely on. COSHH sheets for anything hazardous you're using, and the training evidence behind the competence you've claimed — see our accreditation evidence pack checklist for the full list.
That pack is four or five pages. It is also, crucially, re-usable: the same job pack satisfies the RAMS question for CHAS, SafeContractor, SMAS, Acclaim and the Constructionline health and safety assessment, because they're all assessing against the same SSIP threshold.
Do you need a construction phase plan as well as RAMS?
If you take on the CDM role of principal contractor, or you're the only contractor on site, yes — and it's assessed separately. SSIP Core Criterion 10 requires suppliers in those roles to provide an example construction phase plan from a project in the previous 12 months, and says it should be proportionate to the size and nature of the work, workable and realistic, sufficiently developed to let work start on site, and reviewed as new trades arrive (SSIP Core Criteria).
The HSE's guidance for small builders is in the same spirit: planning must be recorded as a construction phase plan, and the effort devoted to planning should be proportionate to the complexity of the project and the risks involved (HSE, Are you a small builder?). A construction phase plan is not the same document as your RAMS, and swapping one for the other is a reliable way to get a clarification request.
This is informational guidance, not legal or compliance advice — if you're unsure which CDM role you're carrying on a specific job, check with the scheme or a competent adviser.
How many RAMS examples do you need, and how often?
In practice, most small subcontractors need two or three current job packs covering the main work categories they've selected for assessment, plus COSHH assessments where they use hazardous substances. The number varies by scheme and by how many trade categories you tick, so check the question set before you start uploading rather than after.
The repeat is the real cost. The same two or three packs go to your SSIP scheme at renewal, to Constructionline if you hold it, to the Common Assessment Standard if a client asks for it, and then individually to every main contractor who wants RAMS before you set foot on site. Mutual recognition between SSIP schemes helps with the assessment itself — see what SSIP mutual recognition does not cover — but it does nothing about the main contractor emailing you for current RAMS on a Friday afternoon.
Frequently Asked Questions
Are RAMS a legal requirement in the UK?
The risk assessment half is: employers must assess risk under the Management of Health and Safety at Work Regulations 1999, and the HSE states that employers with five or more employees must record their significant findings. Method statements are generally not a specific legal requirement, but CHAS describes them as best practice for complex and high-risk tasks, and clients commonly insist on them.
How many RAMS do I need to submit for an SSIP or CHAS assessment?
Enough to cover the work categories you've selected, which for most small subcontractors means two or three site-specific examples plus any COSHH assessments. SSIP Core Criterion 10 asks for examples from a project carried out within the last 12 months, so quantity matters less than currency and relevance.
Can I use a RAMS template I bought online?
Yes, as a starting structure — templates aren't banned and nobody expects you to design a form from scratch. What gets rejected is a template submitted unedited: no site, no date, no signature and controls that don't match the job. Fill it in against a real project you've done.
Do RAMS expire?
Not formally, but the assessment criteria have a rolling 12-month window — the Once For All Health & Safety SSIP question set used for Constructionline states that evidence must be dated within the last 12 months, and SSIP's Core Criteria ask for examples from a project in the last 12 months. A pack that passed a year ago will usually need replacing with a newer one.
Will the same RAMS work for CHAS, SafeContractor and SMAS?
Usually, yes. All SSIP member schemes assess against the same Core Criteria, so a site-specific, in-date job pack that satisfies one is normally fit for the others. You still have to upload it to each portal separately, and each scheme has its own renewal date — which is where the admin, not the document, becomes the problem. Our guide to one evidence pack for every scheme sets out what overlaps and what doesn't, and the documents hub covers the rest of the pack, including the health and safety policy small contractors need.
Your RAMS don't expire, but the 12-month window does
The trap this guide exposes isn't writing RAMS — you already plan jobs properly, that's why your work stands up. It's that the same two or three dated job packs have to be current, findable and re-sent to every scheme and every main contractor who asks, while each accreditation quietly counts down to its own renewal date. TradeComply keeps your RAMS, insurance and training records in one evidence vault — uploaded once, reused for every scheme, with expiry tracked on the documents themselves — and reminds you at 60, 30 and 7 days before each accreditation renews, with share links so a main contractor gets current certificates without an email chain. The advice above works perfectly well on a spreadsheet and a kitchen table, and plenty of firms run it that way.
Sources
- ssip.org.uk — checked 27/11/2026
- hse.gov.uk — checked 27/11/2026
- chas.co.uk — checked 27/11/2026
- chas.co.uk — checked 27/11/2026
- constructionline.co.uk — checked 27/11/2026
- safecontractor.com — checked 27/11/2026
- hse.gov.uk — checked 27/11/2026
Scheme fees, tiers and question sets change. We re-check our sources and date every guide — how we keep this current.
Related
Pillar · DocumentsContractor Compliance Documents: The Complete ChecklistThe same RAMS, re-uploaded to every scheme
TradeComply keeps your current RAMS, insurance and training records in one evidence vault — uploaded once, reused for every scheme — and tracks each accreditation's renewal date with reminders at 60, 30 and 7 days.
30 days free, then £9.90 a month or £99 a year. Cancel any time. Your documents stay exportable either way.